CO129-135 - Public Offices & Others - 1868 — Page 484

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All AI Reviewed

In 58.08766

Royal Engineer's office

481

Hong Kong 21 March 1888

I have the honor to forward herewith a Plan for a new Lock Hospital on the Site of the present Curt Hospital.

The present Buildings I consider unfit for the purpose and am of opinion that it would be cheaper to build new ones, especially as the Surveyor General informed me that the one now occupied by the Surgeon &c. had been Condemned.

The approximate Estimate is £14,400, an amount I regret that I could not furnish this Plan & Estimate earlier, a day ago when the President was going upon it.

As it was only late that I received the actual data from the Lock Hospital Committee, I was delayed.

C.W. Barry Capt. RE Commanding Royal Engineer

Edit History

2026-05-20 01:36:57 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
In 58.08766 Royal Engineer's office 481 Hong Kong 21 March 1888 I have the honor to forward herewith a Plan for a new Lock Hospital on the Site of the present Curt Hospital. The present Buildings I consider unfit for the purpose and am of opinion that it would be cheaper to build new ones, especially as the Surveyor General informed me that the one now occupied by the Surgeon &c. had been Condemned. The approximate Estimate is £14,400, an amount I regret that I could not furnish this Plan & Estimate earlier, a day ago when the President was going upon it. As it was only late that I received the actual data from the Lock Hospital Committee, I was delayed. C.W. Barry Capt. RE Commanding Royal Engineer
Baseline (Original)
(Copy) In 58.08766 Royal Engineer's office 481 Hong Kong 21 March 1888 I have the honor to forward herewith a Plan for a new Lock Hospital of the present Curt Hospital. _ on the Site The present Buildings I consider unfit for the picrpose and am of opinion that it: would be cheaper to build new ones especially as the Surveyor General informed me that the one now occupied by the Surgeon &c. had been Condemned. to The approximate Estimate £14.400 an amounto I regret that I could not furnish this Plan & Extimate carlier, President a day ago ве go upon. Av it only Late that I received the actual data Lock Hospital Committee Vòng đồng. Jam &c. C.W. Barry Capt. RE Command 5. Ry Engineer B
2026-05-20 01:36:57 · Baseline
View content

(Copy)

In 58.08766

Royal Engineer's office

481

Hong Kong 21 March 1888

I have the honor to forward herewith

a

Plan for

a new

Lock Hospital

of the present Curt Hospital. _

on the Site

The present Buildings I consider unfit for the picrpose and am of opinion that it: would be cheaper to build new ones especially

as the Surveyor General informed me that the

one

now

occupied by the Surgeon &c. had been

Condemned.

to

The approximate Estimate

£14.400

an

amounto

I regret that I could not furnish

this Plan & Extimate carlier,

President

a

day ago

ве

go upon.

Av

it

only

Late

that I received the actual data

Lock Hospital Committee Vòng đồng.

Jam &c.

C.W. Barry Capt. RE Command 5. Ry Engineer